Representative
|
Joe
Baugher's Web Articles
Army Air Forces Statistical
Digest - World War II (Second Printing) (December 1945)
Army
Air Forces Statistical Digest - Supplement Number 1: 1945 (April
1946)
If no specific date of the month is given, then I assume that the first flight, contract, etc is given on the 15th of that month for counting reasons.
“Peak Production Period” for combat aircraft/vehicles is defined as the period when the top 40% of all production is built. It's also a good “rule of thumb” for estimating when that type would be in true mass service.
Prototype Authorization: 10
September 1939
Prototype First Flight: 19
August 1940
Production First Acceptance: 1
February 1941
First Combat Use: Not
Applicable due to Pre-War Development
Peak Production
Period: December 1942
Days from Authorization to First Acceptance: 510 days
Days
from Authorization to Peak Production: 1,192 days
Prototype Authorization: 10
September 1939
Prototype First Flight: 25
November 1940
Production First Acceptance: 22
February 1941
First Combat Use: Not
Applicable due to Pre-War Development
Peak Production
Period: February 1943
Days from Authorization to First Acceptance: 531 days
Days
from Authorization to Peak Production: 1,254
days
Production Authorization: 30 June 1939
Production
First Flight: 16 September 1940
Production First
Acceptance: December 1940
First Combat Use: Not
Applicable due to Pre-War Development
Peak Production Period:
August 1942
Days from Authorization to First Acceptance: 534 days
Days
from Authorization to Peak Production: 1,142 days
Note: The A-20 was a redesign of an existing Douglas aircraft (DB-7) developed for foreign orders; so it's production timing is a bit odd.
Prototype Authorization: 2
June 1941
Prototype First Flight: 10
July 1942
Production First Acceptance: September
1943
Deliveries to Combat Units: June
1944
First Combat Use: 17
September 1944
Peak Production Period: December
1944
Days from Authorization to First Acceptance: 835 days
Days
from Authorization to Deliveries to Combat Units: 1,109 days
Days
from Authorization to First Combat Use: 1,203 days
Days
from Authorization to Peak Production: 1,292
days
Prototype Authorization: 27
April 1939
Prototype First Flight: 29
December 1939
Production First Acceptance: 16
June 1941
Deliveries to Combat Units: Not
Applicable due to Pre-War Development
First Combat Use:
Not Applicable due to Pre-War
Development
Peak Production Period: June
1943
Days from Authorization to First Acceptance: 781
days
Days from Authorization to Deliveries to Combat
Units: Not Applicable due to
Pre-War Development
Days from Authorization to First
Combat Use: Not Applicable due
to Pre-War Development
Days from Authorization to Peak
Production: 1,510 days
Prototype Authorization: 24
August 1940
Prototype First Flight: 21
September 1942
Production First Acceptance: September
1943
Deliveries to Combat Units: 8
May 1944 (Operation Matterhorn units arrive in China)
First
Combat Use: 5 June 1944
Peak
Production Period: November
1944
Days from Authorization to First Acceptance: 1,117
days
Days from Authorization to Deliveries to Combat
Units: 1,353 days
Days
from Authorization to First Combat Use: 1,381
days
Days from Authorization to Peak Production: 1,544
days
Prototype Authorization: 24
August 1940
Prototype First Flight: 7
September 1942
Production First Acceptance: 19
September 1944
Deliveries to Combat Units: July
1945
First Combat Use: July
1945
Peak Production Period: Not
Applicable
Days from Authorization to First Acceptance: 1,487
days
Days from Authorization to Deliveries to Combat
Units: 1,786 days
Days
from Authorization to First Combat Use: 1,786
days
Days from Authorization to Peak Production: Not
Applicable
Piston Engined Fighters
To Be Done Later
Prototype Authorization: 1
November 1951
Prototype First Flight: 25
May 1953
Production First Acceptance: November
1953
Initial Operational Capability: 29
September 1954
Days from Authorization to First Acceptance: 745
days
Days from Authorization to IOC: 1,063
days
Prototype Authorization: 23
December 1969
Prototype First Flight: 27
July 1972
Production First Acceptance: 4
November 1974
Initial Operational Capability: October
1976
Days from Authorization to First Acceptance: 1,777
days
Days from Authorization to IOC: 2,488
days
Prototype Authorization: 13
April 1972
Prototype First Flight: 2
February 1974
Production First Acceptance: August
1979?
Initial Operational Capability: 1
October 1980
Days from Authorization to First Acceptance: 2,680
days
Days from Authorization to IOC: 3,093
days
Prototype Authorization: 31
October 1986
Prototype First Flight: 29
September 1990
Production First Acceptance: 23
October 2002 (Raptor #10)
Initial Operational
Capability: 15 December 2005
Days from Authorization to First Acceptance: 5,919
days
Days from Authorization to IOC: 6,985
days
Prototype Authorization: June
1973
Prototype Handover: February
1976
Production Handover: 28
February 1980
Initial Operational Capability:
Unknown
Midway CVB: 513~ days from being laid down to launched, 178~ days
from launching to commissioning, 690 days average total
Essex CV:
453~ days from being laid down to launched, 165~ days from launching
to commissioning, 617 days average total
Saipan CVL: 363~ days
from being laid down to launched, 371 days from launching to
commissioning; 734 days total (CVL-48 only)
Bogue CVE: 154~ days from being laid down to launched, 250~ days
from launching to commissioning, 383 days average total
Casablanca
CVE: 116~ days from being laid down to launched, 50~ days from
launching to commissioning, 166 days average total
Commencement
Bay CVE: 207~ days from being laid down to launched, 212~ days from
launching to commissioning, 418 days average total
Average CVE:
159~ days from being laid down to launched, 171~ days from launching
to commissioning, 322 days average total
Iowa BB: 942~ days from being laid down to launched, 153~ days
from launching to commissioning, 1095 days average total
South
Dakota BB: 744~ days from being laid down to launched, 215~ days from
launching to commissioning, 959 days average total
North Carolina
BB: 839~ days from being laid down to launched, 324~ days from
launching to commissioning, 1163 days average total
Alaska CB: 627~ days from being laid down to launched, 309~ days
from launching to commissioning, 936 days average total
Baltimore
CA: 502~ days from being laid down to launched, 256~ days from
launching to commissioning, 758 days average total
Cleveland CL:
457~ days from being laid down to launched, 240~ days from launching
to commissioning, 697 days average total
Fletcher DD: 212~ days from being laid down to launched, 152~ days
from launching to commissioning, 364 days average total
Allen M.
Sumner DD: 172~ days from being laid down to launched, 116~ days from
launching to commissioning, 288 days average total
Gearing DD:
196~ days from being laid down to launched, 133~ days from launching
to commissioning, 293 days average total
Average Destroyer:
193~ days from being laid down to launched, 134~ days from launching
to commissioning, 315 days average total
Evarts DE: 111~ days from being laid down to launched, 143~ days
from launching to commissioning, 278 days average total
Buckley
DE: 89~ days from being laid down to launched, 120~ days from
launching to commissioning, 214 days average total
Cannon DE: 158~
days from being laid down to launched, 88~ days from launching to
commissioning, 241 days average total
Edsall DE: 81~ days from
being laid down to launched, 136~ days from launching to
commissioning, 217 days average total
John C. Butler DE: 66~ days
from being laid down to launched, 116~ days from launching to
commissioning, 182 days average total
Rudderow DE: 69~ days from
being laid down to launched, 235~ days from launching to
commissioning, 304 days average total
Average Destroyer Escort:
96~ days from being laid down to launched, 140~ days from launching
to commissioning, 239 days average total
Gato SS: 238~ days from being laid down to launched, 109~ days
from launching to commissioning, 347 days average total
Balao SS:
224~ days from being laid down to launched, 148~ days from launching
to commissioning, 372 days average total
Tench SS: 111~ days from
being laid down to launched, 122~ days from launching to
commissioning, 221 days average total
Average Submarine: 191~
days from being laid down to launched, 126~ days from launching to
commissioning, 313 days average total
Time = 32.69 * Displacement0.32
Where:
Time = Time from keel laying to commissioning in
days
Displacement = Full-Load displacement of the vessel in
long tons.
Notes: Suitable for things ranging from light cruisers to battleships.